Ero sivun ”Saaga2020” versioiden välillä
Siirry navigaatioon
Siirry hakuun
Rivi 58: | Rivi 58: | ||
syyskuu | syyskuu | ||
| | | | ||
+ | * 2.9 Kaapelikourut tulivat labille | ||
+ | * 2.9 Eka kourun lagi on valmis A-tilassa | ||
+ | * 5.9 Kontin valojen sähköjen asennus alkoi | ||
+ | * 7.9 Kaapelikourut on kiinnitetty | ||
+ | * 7.9 Viemäriputki Lottatilassa on huonossa kunnossa | ||
+ | * 7.9 Varaston yksi loistevalaisin hajosi ja vaihdettiin | ||
+ | * 8.9 Korjattu ulkokatto alkoi vuotaa homekohdasta | ||
+ | * 8.9 Verkkokaappi kiinnitettiin yläkertaan | ||
+ | * 10.9 Kattoa korjataan | ||
+ | * 13.9 Imukaapin putkistoa rakennettiin | ||
+ | * 15.9 Lotan 4th akselia testattiin | ||
+ | * 16.9 Kontin katto suojattiin pressulla | ||
+ | * 17.9 Pöytäsahan koulutus | ||
+ | * 19.9 Konttiin asennettiin kaksi liikevaloa | ||
+ | * 20.9 Ison vannesahan terän alatuen kiinnitys petti | ||
+ | * 20.9 Ison vannesahan laakeri ja akseli vaihdettiin | ||
+ | * 20.9 Kuusi loistavalaisimen runkoa kiinnitettiin A-tilaan | ||
+ | * 20.9 Fusionista luovutaan ja siirrytään SolidWorks + MasterCam | ||
+ | * 21.9 Lottaa korjattiin | ||
+ | * 22.9 Laserikoulutus | ||
+ | * 24.9 Uusi printteri saatiin toimimaan | ||
+ | * 26.9 Valaisimet johdotettiin ja rakennettiin väliaikainen viritys. | ||
+ | * 28.9 Optisia kuituja alettiin kytkeä A-tilaan | ||
+ | |||
+ | | | ||
+ | |||
September | September | ||
+ | * 2.9 The cable trays came to the lab | ||
+ | * 2.9 The roof of the first gutter is ready in A-room | ||
+ | * 5.9 The electrical installation of the container lights has started | ||
+ | * 7.9 Cable trays are attached | ||
+ | * 7.9 Sewer pipe in Lotta room condition is in poor condition | ||
+ | * 7.9 One fluorescent lamp in the warehouse broke down and was replaced | ||
+ | * 8.9 The repaired exterior roof began to leak from the mold | ||
+ | * 8.9 The network cabinet was attached upstairs | ||
+ | * 10.9 The roof is being repaired | ||
+ | * 13.9 Suction cabinet piping was built | ||
+ | * 15.9 Lotta's 4th axis was tested | ||
+ | * 16.9 The roof of the container was protected with a tarpaulin | ||
+ | * 17.9 Table saw training | ||
+ | * 19.9 Two motion lights were installed in the container | ||
+ | * 20.9 The attachment of the lower support of the big band saw blade failed | ||
+ | * 20.9 The bearing and shaft of the large band saw were replaced | ||
+ | * 20.9 Six fluorescent lamp bodies were attached to A-room | ||
+ | * 20.9 Quitting Fusion and migrating to SolidWorks + MasterCam | ||
+ | * 21.9 Lotta was fixed | ||
+ | * 22.9 Laser training | ||
+ | * 24.9 A new printer was made to work | ||
+ | * 26.9 The luminaires were wired and a temporary tuning was built. | ||
+ | * 28.9 Optical fibers began to be switched to A-room | ||
+ | |||
+ | |||
|- | |- | ||
| | | | ||
lokakuu | lokakuu | ||
− | + | * 1.10 | |
− | * 3. | + | * 3.10 Uudet hyllyt A-tilaan. Saatiin 36 metriä hyllytilaa |
* 10.10 Uusi pihavalo (33000LUX) asennettiin | * 10.10 Uusi pihavalo (33000LUX) asennettiin | ||
* 15.10 Siirrettiin peltikaapit kemiantilaan | * 15.10 Siirrettiin peltikaapit kemiantilaan | ||
Rivi 79: | Rivi 130: | ||
October | October | ||
− | * 3. | + | * 3.10 New Lundia shelves to A room. 118 feet of "shelf-space" were obtained |
* 10.10 A new yard light (33000LUX) was installed | * 10.10 A new yard light (33000LUX) was installed | ||
* 15.10 Tin cabinets were transferred to the chemical room | * 15.10 Tin cabinets were transferred to the chemical room |
Versio 6. tammikuuta 2021 kello 22.58
Saaga 2020! |
Saga 2020! |
|
tammikuu |
January | |
helmikuu |
February | |
maaliskuu |
March | |
huhtikuu |
April | |
toukokuu |
May | |
kesäkuu |
June | |
heinäkuu |
July | |
elokuu |
August | |
syyskuu |
|
September
|
lokakuu
|
October
| |
marraskuu
|
November
| |
joulukuu
|
|